lag

ResolvedVersion 2007

Dee has attended:
Project Intro Intermediate course

Lag

How do I incorporate this

RE: Lag

Hi Dee

Thank you for your question.

Lag can be added by double clicking a successor task and switching to the predecessor tab then adding the required amount of delay in the lag column.

You can also access the same field by double clicking the arrow connecting the predecessor and successor.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Wed 25 Feb 2009: Automatically marked as resolved.

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.