Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

ms project

ResolvedVersion 2003

Richard has attended:
Project Intro Intermediate course

MS Project

Can I link a task to half way through a predecessor rather than use lag?

RE: MS Project

Hi Richard

Thank you for your question.

Tasks in MS Project only have connections at the start and the finish. To position your successor so it starts half way through the predecessor's duration you would need to use lag. For example in a Finish to Start relationship you might set a lag of -50%

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Wed 25 Feb 2009: Automatically marked as resolved.

MS Project tip:

Gantt Charts

Gantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.