Richard has attended:
Project Intro Intermediate course
MS Project
Can I link a task to half way through a predecessor rather than use lag?
RE: MS Project
Hi Richard
Thank you for your question.
Tasks in MS Project only have connections at the start and the finish. To position your successor so it starts half way through the predecessor's duration you would need to use lag. For example in a Finish to Start relationship you might set a lag of -50%
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew