How do I set critical tasks

RE: Microsoft Project

Hi Sandy

Thanks for your question.

Tasks are calculated by project as critical if they determine the end date of your project and have no slack (float). This means it's not something that we set in the software rather it's calculated for us by Project.

I hope this helps - do let us know if you have any other questions.