Adding a milestone

How do I add a milestone?

RE: Adding a milestone

Hi Jennifer

Thanks for your question - to add a milestone create a task and set its duration to zero. The task on the chart becomes a diamond symbol with a date attached.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.