adding milestone

Forum home » Delegate support and help forum » Microsoft Project Training and help » Adding a milestone

Adding a milestone

resolvedResolved · Low Priority · Version 2003

Jennifer has attended:
Excel Advanced course
Project Intro Intermediate course

Adding a milestone

How do I add a milestone?

RE: Adding a milestone

Hi Jennifer

Thanks for your question - to add a milestone create a task and set its duration to zero. The task on the chart becomes a diamond symbol with a date attached.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes