ResolvedVersion 2003

Sue has attended:
Project Intro Intermediate course

Project 03

HOW CAN YOU SHOW OVERALL PROJECT DURATION ON THE SCHEDULE/ACTIVITIES/TASK SECTION

RE: Project 03

Hi Sue

Thank you for your question - A quick way to do this would be to turn on the Project Summary task. From the Tools menu choose options and select the view tab. From there check the box - show project summary.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.