project

Forum home » Delegate support and help forum » Microsoft Project Training and help » Project 03

Project 03

resolvedResolved · Low Priority · Version 2003

Sue has attended:
Project Intro Intermediate course

Project 03

HOW CAN YOU SHOW OVERALL PROJECT DURATION ON THE SCHEDULE/ACTIVITIES/TASK SECTION

RE: Project 03

Hi Sue

Thank you for your question - A quick way to do this would be to turn on the Project Summary task. From the Tools menu choose options and select the view tab. From there check the box - show project summary.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.07 secs.