Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

predecessors

ResolvedVersion 2007

Joanne has attended:
Project Intro Intermediate course

Predecessors

Please explain the difference between the 4 different predecessor types.

RE: Predecessors

Hi Joanne,

Thanks for your question. Each task has two handles (start and finish). When two tasks are connected you have a choice of four combinations of these handles:

Finish to Start - the default connection
Start to Start - the beginning of the predecessor drives the start of the successor
Finish to Finish - the end of the predecessor drives the end of the successor
and
Start to Finish - the beginning of the predecessor determines the finish of the successor. This usually occurs when the predecessor is later than the successor.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.