Joanne has attended:
Project Intro Intermediate course
Predecessors
Please explain the difference between the 4 different predecessor types.
RE: Predecessors
Hi Joanne,
Thanks for your question. Each task has two handles (start and finish). When two tasks are connected you have a choice of four combinations of these handles:
Finish to Start - the default connection
Start to Start - the beginning of the predecessor drives the start of the successor
Finish to Finish - the end of the predecessor drives the end of the successor
and
Start to Finish - the beginning of the predecessor determines the finish of the successor. This usually occurs when the predecessor is later than the successor.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew