predecessors

Forum home » Delegate support and help forum » Microsoft Project Training and help » Predecessors

Predecessors

resolvedResolved · Medium Priority · Version 2007

Joanne has attended:
Project Intro Intermediate course

Predecessors

Please explain the difference between the 4 different predecessor types.

RE: Predecessors

Hi Joanne,

Thanks for your question. Each task has two handles (start and finish). When two tasks are connected you have a choice of four combinations of these handles:

Finish to Start - the default connection
Start to Start - the beginning of the predecessor drives the start of the successor
Finish to Finish - the end of the predecessor drives the end of the successor
and
Start to Finish - the beginning of the predecessor determines the finish of the successor. This usually occurs when the predecessor is later than the successor.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips


Server loaded in 0.07 secs.