How do I create a milestone?

RE: Milestone

Marion

Enter a zero 0 day in the duration part of the task

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.