Milestone
How do I create a milestone?
RE: Milestone
Carol
Enter a zero 0 day in the duration part of the task
Forum home » Delegate support and help forum » Microsoft Project Training and help » microsft office project 2003 courses in london - Milestone
Carol has attended:
Project Intro Intermediate course
Project Intro Intermediate course
How do I create a milestone?
Carol
Enter a zero 0 day in the duration part of the task
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.