Change Work Time?

How do I change the work time from a 40 hrs week down to 35 hrs per week across all my projects?

Thanks,

Sanna

RE: Change Work Time?

Hi Sanna

Thank you for your question. Starting from a new blank project go to Tools > Options > calendar

set the modify the default start and finish times, along with the hours per day, days per week and month so that you get a 35 hour week.

Click on set as default and close the dialog box. Close the current temporary project without saving it. Now create a new blank project. The settings in options will apply. If you create a 1 day task project will use the hours per day setting and slot it into a calendar using the default start and finish times you set.

I hope this helps - let us know if you have any further questions.

Kind regards,

Andrew

Mon 12 Jan 2009: Automatically marked as resolved.

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.