Forum home » Delegate support and help forum » Microsoft Project Training and help » Critical Path on resource sheet

Critical Path on resource sheet

ResolvedVersion 2003

Peter has attended:
Project Intro Intermediate course
Project Advanced course

Critical Path on resource sheet

How do I get the critical path to be displayed on the Resource Sheet so I can see those tasks that are on the critical path when trying to solve over allocation?

RE: Critical Path on resource sheet

Hi Pete

Thank you for your question and after we discussed this on the course I did go and do some research. I assume you mean Resource Usage View.

Unfortunatly there is no way that I can find to highlight the crtical tasks in Resource Usage view.


Please let me know if you find a work around.

Regards

Laura GB

Thu 4 Dec 2008: Automatically marked as resolved.

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips