task information

ResolvedVersion 2003

Alison has attended:
Project Intro Intermediate course

Task information

When setting up multiple tasks which all have the same duration, how do I update the duration for all tasks at the same time instead of having to go in and update each one individually?

RE: Task information

Hi Alison

Thanks for your question. Try this:
Highlight the tasks you would like to update by selecting them. Right click on the highlighted tasks and choose Task information. In the general tab set the duration you want and click OK. All tasks should now have the duration you entered.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Mon 1 Dec 2008: Automatically marked as resolved.

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips