labelling tiers

ResolvedVersion 2007

Alon has attended:
Project Intro Intermediate course

Labelling tiers

when using the tiers for views, of say Week 1, Week2 etc, how do you start the week count on say week 52, week 53 etc, if you were to start the programme in year 2 of the project for example?

RE: Labelling tiers

Hi Alan

Thank you for your question

Setting your timescale to weeks is used to measure how many weeks have elapsed since the start of your project. It does not meassure whiich week in the year a particualr task falls on. If a task starts on week 10 that is 10 weeks since the project started

It is not therefore possible to reset the week count

Regards

Stephen

Thu 4 Dec 2008: Automatically marked as resolved.

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.