when using the tiers for views, of say Week 1, Week2 etc, how do you start the week count on say week 52, week 53 etc, if you were to start the programme in year 2 of the project for example?
RE: Labelling tiers
Hi Alan
Thank you for your question
Setting your timescale to weeks is used to measure how many weeks have elapsed since the start of your project. It does not meassure whiich week in the year a particualr task falls on. If a task starts on week 10 that is 10 weeks since the project started
It is not therefore possible to reset the week count
Regards
Stephen