paula has attended:
Project Intro Intermediate course
Earned value formulas
What are earned value formulas?
RE: Earned value formulas
Hi Paula
Thanks for your question. A starting point for Earned Value would be to look at some simple calculations:
Budgeted Cost of Work Scheduled (BCWS) - our budget (or baseline)
Budgeted Cost of Work Performed (BCWP) - the agreed resource rate applied to work carried out
Actual Cost of Work Performed (ACWP) - what we really paid for the work carried out.
Once we have these figures we can do some simple analysis. For example :
Performance Index:
BCWP/ACWP = CPI or Cost Performance Index. Less than 1 the project is over spending
BCWP/BCWS = SPI or Schedule Performance Index. Less than 1 means the project is behind schedule.
These calculations offer a starting point. I hope this helps - do let us know if you have any further questions.