Is there a way of working out the amount a task has been split by? And is there a way to assign a resourse to a split?
Thank you?
RE: Split tasks
Hi Derren
Thank you for your question
To calculate the length of a split you need to create two customised duration fields. The first field calculates the number of days between the start and finish. Click on Tools-Customise-Fields. Select Duration 1 and click on the formula button. Insert a projdatediff function, where date 1 is the start date and date 2 is the finish date, leave the calendar field blank.
Then create a second customised date field, date2 with a formula that subtracts duration from duration1
This will give you the length of the split. You can then insert it as a column in your gantt chart
Regards
Stephen