how do you set more than 1 baseline then view them simultaneously?

RE: baselines

Hi Stewart

You can save more than one baseline by going to tools > tracking > save baseline and from the top baseline drop-down choosing the baseline field to store your current plan.

You can see more than one baseline by going to the view menu and choosing more views then selecting multiple baselines Gantt (which shows up to 4)

I hope this is helpful - let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.