How can you start a successor task only after a predecessor task is 75% complete?
RE: Task setup
Hi Alpa
Thanks for your question. You can double click on your successor task and give it's relationship to the predecessor a minus 75% lag. Project will calculate negative lag (lead time) of 75% of the duration of the predecessor and position your successor task accordingly.
I hope this helps. Let us know if you have more questions.
Kind regards,
Andrew