RE: Project
Hi Paul
thanks for your question. One way you could enter actual completion is to select your task then from the Tools menu choose Tracking > update task
In the dialog that appears record how much has been done (actual) and any remaining duration and click OK. You'll also see the dialog box can accept actual start and finish dates if you prefer.
I hope this is helpful - let us know if you have any other questions.
Kind regards
Andrew