RE: Microsoft Project
Hi DJ
Thanks for your question. Starting in the Gantt view. In Project going to the Window menu then choose Split. Project displays the Gantt chart in the top half of the screen and below the split line shows a form that provides more details about the activity selected above the split. The form allows you to assign resources and control settings such as the task type.
I hope this is helpful. Let us know if you have any further questions.
Kind regards,
Andrew