How do you remove a split from a task

RE: Splits


On the chart side of Gantt Chart, click and drag the split portion after split of the task back to the first portion of the task. The two sections will join back together when you release the mouse button.

Laura

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.