Linking calenders

How do you link calenders running simultaneously?

RE: linking calenders

Hi Pauline

Individual calendars remain independent of each other.
The closest example of one calendar driving another is on the resource sheet where you set the calendar that will be the base for each resource (by default this is set to standard).

Hope this helps. Do let us know if you have any other questions.

Kind regards,

Andrew

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.