What is the most affective way to get info from Excel to project
RE: Software
Hi Robert,
Thank you for your question.
There are a couple of ways. If the data in Excel is arranged in columns and includes data like task names and durations, you can copy and paste the data directly into your project file in the task sheet.
The second way is to use the File Open command and navigate and choose the excel file you want. You will then get the Import wizard and you will have to map the fieldnames in the spreadsheet with the relevant field names in Project.
I hope this answers your question.
Regards