Graham has attended:
Project Intro Intermediate course
Microsoft Project
When I go back to work remind me what needs to be carried out in preparation
RE: Microsoft Project
Hi Graham
Thank you for your question. In short, the following needs to be carried out to prepare your project environment
1. Set up the start date for the project. To do this click on Project - Project information and choose a start date
2. Set up you working time calandars by clicking on Tools-Change working time and editing the required base calendar. You can then set this as the project default calendar by clicking on Project-Project Information and selecting the base calendar in the calendar combo box
3. Finally, you need to click on Tools-Options-Calandar and set the start and end times as well as hours per day and hours per week to match the settings on your base calendar
Regards
Stephen