Forum home » Delegate support and help forum » Microsoft Project Training and help » Project Information - Start Date / End dates

Project Information - Start Date / End dates

ResolvedVersion 2003

Sudeep has attended:
Project Intro Intermediate course

Project Information - Start Date / End dates

(Post removed at the request of the poster)

RE: Project Information - Start Date / End dates

Hi Sundeep

Thank you for your question

There are a number of possible causes here, but it is difficult to identify specific causes without seeing the file.

If possible, could you email the file to me at StephenATstl-training.co.uk and i will examine the rpoblem and get back to you

Regards

Stephen

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips