How do you change working hours after the project has been created? i.e. You have discovered that the working hours have been entered incorrectly.

RE: Working Hours

Hi sarah

Thank you for your question

Changing your project default calendar after you have entered tasks into your project is possible, but will have consequences for the duration of the tasks.

For example if you create a task based on the standard 8 hour day calendar, and sets its duration to one day, project will assume that there is one day of 8 hours involved.

If you then change the calendar to the 24 hour calendar, project will still assume that the task is only 8 hours duration. However, as a day now comprises 24 hours, 8 hours is only equal to 1/3 of a day and so the duration will change to accommodate this.

As a consequence you may need to alter task durations to compendate for this

Regards

Stephen

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.