As an event manager I have a deadline that I have no choice but to meet, i.e. the event date. Is it o.k for me to set the project up so that it HAS to end on the event date no matter what? So, all tasks can be flexible but must be completed by event date.
RE: Project
Yes. Bear in mind however that when something slips in the Project you will receive warning messages that Project cannot honour the MUST FINISH ON constraint and will have to adjust the schedule yourself in order to keep the constraint in place. This means tight monitoring of the schedule while tracking.