Filtering resources
How can I filter tasks by resource name
RE: filtering resources
Hi Linda
Thanks for your question.
To quickly filter your tasks by resource name make sure you are in a task orientated view (such as the Gantt Sheet) then from the Project menu choose Filtered for and from the menu choose "Using Resource". This will prompt you to choose a resource and once you have clicked OK the tasks are filtered to show only those to which the resource has been assigned.
Hope this helps - let me know if you have any further questions.