How can I filter tasks by resource name

RE: filtering resources

Hi Linda

Thanks for your question.

To quickly filter your tasks by resource name make sure you are in a task orientated view (such as the Gantt Sheet) then from the Project menu choose Filtered for and from the menu choose "Using Resource". This will prompt you to choose a resource and once you have clicked OK the tasks are filtered to show only those to which the resource has been assigned.

Hope this helps - let me know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.