Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

lead times

ResolvedVersion 2007

David has attended:
Project Intro Intermediate course
Project Advanced course

Lead times

can you explain more about laed time, lag and negative lags.

RE: Lead times

Hi David

Thank you for your question

Lag time is where there is delay between the start or finish of a predecessor task and the start or finish of its sucessor. For example if 2 tasks are linked on a simple finish to start basis, and if the sucessor cannot start until 2 days after the predecessor is complete, then the relationship has a two day lag.

Lead time is the reverse of lag time. Imagine in the above example that it was possible to start the sucessor task not when the predecessor is complete, but when it is 50% complete. In this instance the relationship has a 50% lead. In MS Project lead times are entered as negative lags.

Hope this is useful

Regards

Stephen

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.