microsoft project training - Repeat Meetings

ResolvedVersion Standard

Ruth has attended:
Project Intro Intermediate course

Repeat Meetings

How do I schedule meetings to take place monthly for 6 months without effecting the finish date of the project? Some tasks may be dependant on these meetings individually but not the end date of the project as a whole.

RE: Repeat Meetings

1. go to Insert on the menu bar
2. select Recurring task
3. enter your information in here

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips