ResolvedVersion 2007

Claire has attended:
Project Intro Intermediate course
Excel Introduction course
Excel Intermediate course

Calendars

I have my calendar set to the standard base setting, I type in "1 day" but when I look back at it, it keeps saying "0.94 days" instead.

Please can you let me know what I can do to recitify this.
Thanks.

RE: Calendars

Hi Calire

Thank you for your question

This is most likely caused by one of the following:

1. The calendar settings found in Tools-Options- Calendar do not match the settings specified in your standard base calendar. Make sure that the day start and end times, together with hours per day and hours per week match

2. If you have resources allocated to the task and one of the resources' calendars differes from the standard calendar then this too will change the duration of the task as the individual resource calendar overides the standard project calendar.

3. You specified a duration for the task, and then changed the base calendar. This too could cause discrepencies in duration.

Hope one of the above proves helpful, if not please let me know so I can explore other avenues

Regards

Stephen

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.