microsoft project training in london - How do I create a hammock task?

ResolvedVersion Standard

Jon has attended:
Project Intro Intermediate course

How do I create a hammock task?

See above

RE: How do I create a hammock task?

Select the end date of 1 task and copy it then paste special and link the end date into the start date of another task

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.