RE: How do I create a hammock task?
Select the end date of 1 task and copy it then paste special and link the end date into the start date of another task
Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training in london - How do I create a hammock task?
Select the end date of 1 task and copy it then paste special and link the end date into the start date of another task
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question.
Our Microsoft Qualified trainers will then respond within 24 hours (working days).
Frequently Asked Questions
What does 'Resolved' mean?
Any suggestions, questions or comments? Please post in the Improve the forum thread.
In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.