best way of using MS Project to track best practice of planning techniques and using these to report

RE: Reporting

Hi Rene

Thanks for your question - you may find the following information from Microsoft of interest. They have created a roadmap for Project Managers to help them manage their projects using MS Project 2003.

You can find the information online at
http://office.microsoft.com/en-gb/project/HA010745311033.aspx

I hope this is helpful - let us know if you need further information.

Kind regards,

Andrew

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips