How do I remove Saturday and Sunday from my view? Or, could I structure my view Monday-Saturday

RE: Project

Hi Fleur

Thanks for your question. Saturday and Sunday will always be in the calendar - the only way not to see them is to zoom the timescale to a view like Months.

Hope this was helpful

Kind regards,

Andrew
(PS your notes will be sent to you this week)

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips