Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

critical path

ResolvedVersion 2007

Samir has attended:
Project Intro Intermediate course

Critical Path

How do i create a critical path

RE: Critical Path

Hi Samir,

You don't create a critical path in Project. As you build your project and have all the links in place, the critical path is calculated automatically for you.

A critical task is a task that if delayed, has an impact on the start or project finish dates. These tasks appear in red when you change your view to Tracking Gannt.

I hope this answers your question.

Regards

Simon

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.13 secs.