RE: Critical Path
Hi Samir,
You don't create a critical path in Project. As you build your project and have all the links in place, the critical path is calculated automatically for you.
A critical task is a task that if delayed, has an impact on the start or project finish dates. These tasks appear in red when you change your view to Tracking Gannt.
I hope this answers your question.
Regards
Simon