ResolvedVersion Standard

Martin has attended:
Project Intro Intermediate course

MS Project

I am having trouble sorting task duration in ascending order. Can anyone tell me how to do it?

Thanks

Martin

RE: MS Project

Hi Martin,

If you select the Project menu, then choose Sort followed by the Sort By option. In the first box choose the Duration field from the list and make sure the Ascending option is selected.

I hope this has answered your question.

Regards

Simon

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)