Resource allocation

how do you allocate resources to tasks which will be part-time, i.e. involving periods of waiting?

RE: resource allocation

Hi Stewart

Thankyou for your question

The best approach would be to open the resource usage sheet and then go to the assignment in question. You can manually adjust the hours worked per day to achieve exactly the effect that you need.

However, as you will be altering the number of hours worked and you need Project to alter the percentage allocation of the resource, it would be a good idea to set the task type to "Fixed Duration", as if left as "fixed units" project might under certain circumstances alter the overall duration instead.

Hope this helps

Regards

Stephen

MS Project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.