Steve has attended:
Project Intro Intermediate course
Change Working time - adding, deleting or renaming calendars
How do you delete or rename calendars once you have created new ones under the 'Change working time' button under 'Tools'?
RE: Change Working time - adding, deleting or renaming calendars
Hi Steve
Thankyou for your question. If you click on Tools-Organiser and select the calendars tab you will be given a complete list of the calendars in both the current project and the global tremplate.
You can then delete and rename the calendars as required. You can also copy calendars from the current project to the global template, thus making them available for all future projects created on that machine.
Hope this is useful
Regards
Stephen