Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

active project

ResolvedVersion Standard

Fiona has attended:
Project Intro Intermediate course

Active project

Once I've set up all tasks etc and my project is underway, is it then possible to insert additional tasks if there's anything I've forgotten to include at initial set up?

RE: Active project

Hi Fiona

Thankyou for your question

There is no limitation on what you can add after you have baselined your project

Any tasks you add will appear without a corresponding baseline. If they have successor tasks that already exist then the tasks of course might be delayed, causing a variance in the schedule.

If your new tasks are to be resourced, then this will also cause cost variances.

If the project has been baselined, but little or no progress made on the existing tasks, it might be better to remove the baseline, add the new tasks and then baseline the project again. This would include the new tasks in the baselined schedule and budget.

Regards

Stephen

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.