Date jumps from 2011 to 2012 in October
Hi,
I wonder if you can confirm if this is a bug in Project 2010 (I am pretty sure it was in 2007)?
As you can see, the highlighted task finishes on 04/11/11. However, the Gantt bar ‘jumps to 2012! It does this in the Team Planner view as well.
See the image below for more detail.
http://i42.tinypic.com/2zr2jv4.jpg
Any thoughts?
Thanks
Nav
RE: Date jumps from 2011 to 2012 in October
Hi Navraj
Thank you for your question. One thing that might be worth checking is the financial year setting. Take a look at File > Options > Schedule and take a look at what has been set for Fiscal Year starts in (the third drop down). Most often this is set to January - a different month can make cause the Timescale to look odd. Let me know what you find.
Kind regards,
Andrew