What does WBS stand for?
RE: Project Management
Hi Cosmin
thank you for your question - WBS stands for Work Breakdown Structure. A Hierarchical method for organising all the activities within your plan. Starting from the top, working down the page, breaking the main and intermediate deliverables into smaller work packages. General advice would suggest that you stop breaking items down when they may result in activities of less than one day's duration.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew