How do I get a probabilistic schedule out of the software so that I see what the earliest and longest the project could be.

Edited on Thu 25 Sep 2008, 17:00

RE: Project management

Hi Dominique

Your tasks in Project will probably already be set to start as soon as possible, so Project will try and show you the earliest finish date by default. To find out how long you can delay tasks without impacting surrounding tasks or the project itself take a look at the the Schedule table.
Right click on the select all square (above the row numbers and to the left of the column headers) and from the list of tables that appears choose Schedule. You will find the late start information calculated by Project.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

 

Training courses

 

Training information:

Welcome. Please choose your application (eg. Excel) and then post your question.

Our Microsoft Qualified trainers will then respond within 24 hours (working days).

Frequently Asked Questions
What does 'Resolved' mean?

Any suggestions, questions or comments? Please post in the Improve the forum thread.


 

Management Training tip:

Task List or To Do List

Don't confuse yourself with too many tasks on a to do list. The Task List is all the things that require attention, whether by you or others, now or later. The To Do list is your immediate daily plan, and is a subset of your Task List.

Keep your To Do list to no more than 5 major items.

View all Management Training hints and tips


Server loaded in 0.05 secs.