Project
How to see multiple resources assignments for different project plans
RE: project
Hi Simon
Thanks for your question. One of the views you can use to see your resource assignements is the Resource Usage view (view > resource view). This will show tasks grouped by resources and includes tasks in linked projects.
Hope this helps - do let us know if you have any further questions.