Joanne has attended:
Project Intro Intermediate course
Project Advanced course
Recurring Tasks
We are entering weekly meetings as a recurring task but it seems you have to add resources to each meeting week by week. Is there a way to allocate resources to a recurring task so they are linked to each event?
RE: Recurring Tasks
Hi Joanne
Thank you for your question - you would need to add the resources manually. The recurring task tool creates the events rather the assignments.
I'm sorry that I can't be of more help. Do let us know if you have any further questions.
Kind regards,
Andrew