how do we set non working days on the calendar

RE: MS Project

Hi Christine

Thanks for your question.

From the menu choose Tools > change working time
In the dialogue box that appears click (or control click) to select the days to mark as non working and choose the Non-working time radio button.

I hope this helps - do let us know if you have any further questions.

Kind regards,


Andrew

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.