Forum home » Delegate support and help forum » Microsoft Project Training and help » Project - Free Format column?

Project - Free Format column?

ResolvedVersion 2003

Philip has attended:
Project Intro Intermediate course

Project - Free Format column?

Hi

Is there a way of free formatting a column in project so that I can add my own labels which correspond to the specific tasklists I have?

Thanks and regards
Phil

RE: Project - Free Format column?

Hi Phil,

If you double click on the column heading, you will be presented with the column definition box. If you enter a new word or words in the Title box, this will become the new column heading.

I hope this answers your question.

Regards

Simon

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes