Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

STL - Formerly Best Training Solutions Through Learning
TrustPilot
Excellent
Request Callback We will call you back
0207 987 3777 Call for assistance
Your Basket Basket is empty
microsoft-project-training - linking several tasks

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft-project-training - Linking several tasks

microsoft-project-training - Linking several tasks

ResolvedVersion Standard

Cesar has attended:
Project Introduction course

Linking several tasks

How to link several small tasks into a large task

RE: linking several tasks

Hi Cesar

One way to combine several tasks is to create a summary task.

Above the list of tasks that you'd like to group together insert a new blank line and enter the name of the group or summary. Then select the tasks you'd like to include in this group and click on the indent button on the toolbar. The tasks will be indented slightly to the left and the summary task will be boldened.

Hope this helps - do let us know if you have any other questions.

Kind regards

Andrew

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips