resource over allocation

Forum home » Delegate support and help forum » Microsoft Project Training and help » Resource over allocation

Resource over allocation

ResolvedVersion 2016

David has attended:
Project Introduction course

Resource over allocation

Our organisation has a lot of projects that have overlapping tasks or tasks that start at the same time and we allocate people to work on multiple tasks at the same time. This is possible for them to manage within their daily work but I keep getting over allocation errors. Is there a way I can allocate them to work on multiple tasks at the same time?
Thanks

RE: Resource over allocation

Hi David,

Project has a very literal view on resourcing, it allocates them 100% to that day/task.

One way is to Right click on the Task and choose Assign Resources.

(Other way is to click on View tab and click "Details")

In this box you can adjust the "Units" of that person to 20%

If you do this method, you can use that person on 5 tasks.

It does mean you have to adjust all previous conflicting allocations to 20%.

Does that give you a work around to the problem?

Kind regards

Richard Bailey
Microsoft Certified Trainer

Best STL - https://www.stl-training.co.uk
98%+ recommend us

London's leader with UK wide delivery in Microsoft Office training and management training to global brands, FTSE 100, SME's and the public sector

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.