Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training seminar - Microsoft Project

microsoft project training seminar - Microsoft Project

ResolvedVersion Standard

Cormac has attended:
Project Intermediate course

Microsoft Project

What is a baseline?

RE: Microsoft Project

It is a sporting reference

RE: Microsoft Project

Hi Cormac

A baseline takes a snapshot of your project plan prior to work commencing. This way you can always compare your current plan with what was orginally agreed (the baseline) and see where you are ahead or behind schedule.

Go to tools > tracking > then save baseline to store the baseline info. A quick way to see it is to switch to the tracking gantt view.

Hope this helps - do let us know if you have any other questions.

Kind regards,

Andrew

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.