change working hours

TrustPilot

starstarstarstarstar Excellent

  • Home
  • Courses
  • Promotions
  • Schedule
  • Formats
  • Our Clients

Forum home » Delegate support and help forum » Microsoft Project Training and help » Change Working Hours

Change Working Hours

resolvedResolved · Low Priority · Version 2003

Joanne has attended:
Project Intro Intermediate course
Project Advanced course

Change Working Hours

Is there a way of changing one persons working hours? I have set the project calender to the normal working week - monday to friday 0800 - 1700 but I have one resource who works different hours to everyone else. He has a set working week but I seem to only be able to change his hours day by day.

RE: Change Working Hours

Hi Joanne,

Thank you for your question.

Go to Resource sheet view and right click over the resource in question and choose Resource Information. Select Change Working Time from the first tab and select the column letters.

So if you wanted to set the hours for Monday to Friday to 9am to 6.30pm, then highlight the column letters across from M to F and then edit the working times.

I hope this answers your question.

Let me know how you get on.

Regards

Simon

RE: Change Working Hours

All sorted, Thank you.


 

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips


Server loaded in 0.06 secs.