David
Thanks for the question,
Enter a zero 0 day in the duration part of the task
Tracy
Solutions Through Learning
Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project courses london - Milestone
David
Thanks for the question,
Enter a zero 0 day in the duration part of the task
Tracy
The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)