RE: Project 2003
set a duration as a zero date
Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training courses - Project 2003
set a duration as a zero date
In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.